Project Cost Estimation Accuracy

Many time I experienced a dilemma when user is asking for estimated cost of Project instantly. As a project manager, It become utmost importance to say anything because, if it is over estimated you are going to have a bad name or may loose the project. If it is under estimated than your project will be a loss making lad. In my opinion to overcome such situation, we should give estimated cost but also update the user about the Accuracy tolerance in Cost Estimation. This will help user to be ready for listening something else when actual cost estimating is done. This will also help a project manager to throw away the unwarranted burden over head. As per prevalent market conditions, following is the accuracy in project cost estimation.

1. Rough Order of Magnitude - (-50% to 100% )against projected cost estimation.

2. Order of Magnitude  - (-25% to 75%).

3. Budgeted Estimates - (-10% to 25%).

4. Definitive Estimates - (-10% to 15%).

Project Manager must understand the time of giving estimates and accordingly explain about the accuracy. The magnitude of estimation accuracy can be decided based on the project phase. The more close you are to the project definitive estimation more accuracy is available.

Please do not forget that the progress is project and cost of changes is directly proportional.

Aman

Comments

  1. This is based on what edition version of PMP edition?

    ReplyDelete

Post a Comment

Popular posts from this blog

How to Enable ULTIMATE Performance Mode in Windows 10. Speed Up Your PC

How to Enable ULTIMATE Performance Mode in Windows 10 to Speed up Computer.